Monthly CORE meetings are scheduled to bring the state, the architects, and other key personnel together with district administration. This is a critical step in ensuring that the needs of our students are met through the design. In December of 2019, visioning work began with teachers, aides, coaches and others to help shape the project design. In November of 2019, the architectural firm, Elevar Design Group was selected for the Middle School construction and facilities renovation project. In August of 2019, East Clinton was given a final approval from the state controlling board to move forward with the project. There are also portions of the project that are locally funded initiates. Ohio is contributing 52% of the co-fundable portion of the project. This project is in conjunction with Ohio Facilities Construction Commission. Along with these renovations a new middle school will be constructed. In November of 2018 a bond issue was passed for the renovation of both elementary school buildings and of the high school.